Docket

40869

dTechs EPM Ltd. v. British Columbia Hydro and Power Authority, et al.

(Federal) (Civil) (By Leave)

Judgments on applications for leave to appeal are rendered by the Court, but are not necessarily unanimous.

Proceedings
Date Proceeding Filed By
(if applicable)
2024-11-08 Certificate of taxation issued to, Michael Crichton
2024-11-08 Decision on the bill of costs, in the amount of $1,159.22, Reg
2024-11-08 Submission of the bill of costs, Reg
2024-02-28 Bill of costs, UNDER REVIEW, Completed on: 2024-03-07 British Columbia Hydro and Power Authority
2024-02-15 Copy of formal judgment sent to Registrar of the Court of Appeal and all parties
2024-02-15 Judgment on leave sent to the parties
2024-02-15 Judgment of the Court on the application for leave to appeal, The application for leave to appeal from the judgment of the Federal Court of Appeal, Number A-121-21, 2023 FCA 115, dated May 26, 2023, is dismissed with costs to the respondent British Columbia Hydro and Power Authority
Dismissed, with costs
2024-01-15 All materials on application for leave submitted to the Judges, for consideration by the Court
2023-12-01 Certificate (on limitations to public access), 23B-Reply dTechs EPM Ltd.
2023-10-10 Applicant's reply to respondent's argument, (Book Form), REQUIRED:
- 23B (rec'd 2023-12-01), Completed on: 2023-12-05, (Printed version filed on 2023-10-10)
dTechs EPM Ltd.
2023-10-02 Notice of name, (Letter Form) British Columbia Hydro and Power Authority
2023-09-28 Certificate (on limitations to public access), (Letter Form), 23A/23B, (Printed version filed on 2023-10-05) Awesense Wireless Inc.
2023-09-28 Notice of name, (Letter Form), (Printed version filed on 2023-10-05) Awesense Wireless Inc.
2023-09-28 Notice of change of solicitor, (Letter Form), (Printed version filed on 2023-10-05) Awesense Wireless Inc.
2023-09-28 Respondent's response on the application for leave to appeal, (Letter Form), Completed on: 2023-10-05, (Printed version filed on 2023-10-05) Awesense Wireless Inc.
2023-09-28 Certificate (on limitations to public access), (Letter Form), 23B British Columbia Hydro and Power Authority
2023-09-28 Certificate (on limitations to public access), (Letter Form), 23A British Columbia Hydro and Power Authority
2023-09-28 Respondent's response on the application for leave to appeal, (Book Form), REQUIRED:
- Notice of name, Completed on: 2023-09-29, (Printed version filed on 2023-09-29)
British Columbia Hydro and Power Authority
2023-08-29 Letter acknowledging receipt of a complete application for leave to appeal, FILE OPENED 2023-08-29
2023-08-25 Certificate (on limitations to public access), Amended 23A-23B rec'd 2023-10-02 dTechs EPM Ltd.
2023-08-25 Notice of name dTechs EPM Ltd.
2023-08-25 Application for leave to appeal, (Book Form), (2 volumes), Amended 23A rec'd 2023-09-29, Completed on: 2023-08-25, (Printed version filed on 2023-08-25) dTechs EPM Ltd.